Final Pressure Test: Happy Customers
After every gas heater installation or pipe work, a Final Pressure Test is conducted to ensure the system is 100% leak-free and compliant with Singapore regulations.
🧪
Final Pressure Test
SS 608:2024 Compliance
After completing the Gas Pipe Above False Ceiling Repair, our team performs a final pressure test to ensure the system is safe and gas-tight.
📏
Test Pressure
450 mm w.g.
⏱️
Test Duration
5 Minutes
✅
Purpose
Leak Check
The gas piping system is pressurized to 450 mm w.g. for 5 minutes, in accordance with Singapore Standard SS 608:2024. During this period, we carefully monitor for any pressure drop or leakage.
This test confirms that the installation is leak-proof, safe for use,
and fully compliant with regulations before handing over to the homeowner.